| Action Date | Action Description |
|---|---|
| Jun 01, 2020 | Assent Application Received |
| Jun 01, 2020 | Administrative Review for Completeness |
| Jun 02, 2020 | Project Manager |
| Jun 05, 2020 | Additional Information Received |
| Jun 11, 2020 | Application Accepted |
| Jun 11, 2020 | Project Manager |
| Jun 11, 2020 | Eng Team Review for Completeness |
| Jul 13, 2020 | Additional Information Received |
| Jul 14, 2020 | Typist for Processing |
| Jul 14, 2020 | Executive Sign Off |
| Jul 14, 2020 | Sent to Photo Copy |
| Jul 14, 2020 | Permit Approved |
| Jul 14, 2020 | Engineering Report |
| Aug 26, 2020 | Land Evidence Date |
| Apr 08, 2021 | HPHC Historical Preservation No Effect |
| Apr 08, 2021 | HPHC Review Pending |