| Action Date | Action Description |
|---|---|
| Sep 02, 2020 | Assent Application Received |
| Sep 14, 2020 | Administrative Review for Completeness |
| Sep 23, 2020 | Additional Information Requested from Applicant |
| Oct 05, 2020 | Additional Information Received |
| Oct 09, 2020 | Application Accepted |
| Oct 09, 2020 | Project Manager |
| Oct 09, 2020 | Bio Team Review for Completeness |
| Oct 23, 2020 | Additional Information Requested from Applicant |
| Oct 23, 2020 | Additional Information Received |
| Oct 26, 2020 | HPHC Historical Preservation No Effect |
| Oct 26, 2020 | HPHC Review Pending |
| Oct 27, 2020 | Biologist Report |
| Oct 27, 2020 | Additional Information Requested from Applicant |
| Oct 27, 2020 | Additional Information Received |
| Oct 27, 2020 | Typist for Processing |
| Oct 27, 2020 | Executive Sign Off |
| Oct 27, 2020 | Sent to Photo Copy |
| Oct 27, 2020 | Permit Approved |
| Nov 05, 2020 | Land Evidence Date |