| Action Date | Action Description |
|---|---|
| Dec 11, 2020 | Assent Application Received |
| Dec 11, 2020 | Administrative Review for Completeness |
| Dec 14, 2020 | Bio Team Review for Completeness |
| Dec 14, 2020 | Application Accepted |
| Dec 14, 2020 | Project Manager |
| Jan 21, 2021 | HPHC Review Pending |
| Jan 21, 2021 | HPHC Historical Preservation No Effect |
| Jan 22, 2021 | Stipulation Package from Biologist |
| Jan 22, 2021 | Biologist Report |
| Jan 25, 2021 | Typist for Processing |
| Jan 25, 2021 | Executive Sign Off |
| Jan 25, 2021 | Sent to Photo Copy |
| Jan 25, 2021 | Permit Approved |
| Mar 26, 2021 | Land Evidence Date |
| Sep 07, 2021 | Modification Request |
| Sep 13, 2021 | Administrative Review for Completeness |
| Sep 17, 2021 | Bio Team Review for Completeness |
| Sep 17, 2021 | Project Manager |
| Oct 06, 2021 | Biologist Report |
| Oct 06, 2021 | Stipulation Package from Biologist |
| Oct 13, 2021 | HPHC Review Pending |
| Oct 13, 2021 | HPHC Historical Preservation No Effect |
| Oct 18, 2021 | Typist for Processing |
| Oct 18, 2021 | Executive Sign Off |
| Oct 18, 2021 | Sent to Photo Copy |
| Oct 18, 2021 | Modification Approved |
| Nov 12, 2021 | Land Evidence Date |