| Action Date | Action Description |
|---|---|
| Apr 15, 2021 | Assent Application Received |
| Apr 19, 2021 | Administrative Review for Completeness |
| Apr 19, 2021 | CHA Worksheet received |
| May 03, 2021 | Bio Team Review for Completeness |
| May 03, 2021 | Application Accepted |
| May 03, 2021 | Project Manager |
| May 04, 2021 | Engineering Report |
| May 04, 2021 | Stipulation Package by Engineer |
| May 04, 2021 | CHA -- application modified due to CHA info |
| May 06, 2021 | Executive Sign Off |
| May 06, 2021 | Sent to Photo Copy |
| May 06, 2021 | Permit Approved |
| May 06, 2021 | Typist for Processing |
| May 17, 2021 | HPHC Review Pending |
| May 17, 2021 | HPHC Historical Preservation No Effect |
| Aug 20, 2021 | Land Evidence Date |