| Action Date | Action Description |
|---|---|
| Aug 27, 2013 | Assent Application Received |
| Aug 27, 2013 | Administrative Review for Completeness |
| Oct 03, 2013 | Team Review for Completeness |
| Oct 03, 2013 | Application Accepted |
| Dec 04, 2013 | Additional Information Received |
| Dec 19, 2013 | Plans Received |
| Jan 02, 2014 | Engineering Report |
| Jan 02, 2014 | Biologist Report |
| Jan 03, 2014 | Typist for Processing |
| Jan 03, 2014 | Permit Approved |
| Jan 06, 2014 | Executive Sign Off |
| Jan 06, 2014 | Sent to Photo Copy |
| Jan 16, 2014 | HPHC Historical Preservation No Effect |
| Jan 17, 2014 | Land Evidence Date |
| Jan 31, 2014 | Water Quality Certification |
| Nov 29, 2017 | Modification Request |
| Nov 29, 2017 | Administrative Review for Completeness |
| Nov 30, 2017 | Team Review for Completeness |
| Nov 30, 2017 | Application Accepted |
| Dec 18, 2017 | Biologist Report |
| Dec 18, 2017 | Typist for Processing |
| Dec 18, 2017 | Executive Sign Off |
| Dec 18, 2017 | Sent to Photo Copy |
| Dec 18, 2017 | Modification Approved |
| Jan 08, 2018 | HPHC Historical Preservation No Effect |
| Mar 07, 2018 | Duplicate Original Assent requested/mailed |
| Mar 09, 2018 | Land Evidence Date |
| Mar 20, 2019 | Extension of Permit Request |
| Apr 25, 2019 | Enforcement Compliance Inspection Required |
| Apr 25, 2019 | Process Extension |
| Apr 25, 2019 | Extension Approved |
| May 04, 2020 | Extension of Permit Request |
| Jun 02, 2020 | Enforcement Compliance Inspection Required |
| Jun 03, 2020 | Process Extension |
| Jun 03, 2020 | Extension Approved |
| Apr 13, 2021 | Extension of Permit Request |
| May 03, 2021 | Category A assigned |
| Jul 12, 2021 | Enforcement Compliance Inspection Required |
| Jul 27, 2021 | Semi-Monthly Meeting Date Scheduled |
| Jul 27, 2021 | Council Approval - Extension Granted |
| Aug 24, 2021 | Extension Approved |
| Aug 24, 2021 | Process Extension |