| Action Date | Action Description |
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| Aug 13, 2021 | Assent Application Received |
| Aug 17, 2021 | Administrative Review for Completeness |
| Aug 19, 2021 | Bio Team Review for Completeness |
| Aug 19, 2021 | Application Accepted |
| Aug 19, 2021 | Project Manager |
| Aug 19, 2021 | Category A* (Docks) |
| Sep 03, 2021 | HPHC Historical Preservation No Effect |
| Sep 03, 2021 | HPHC Review Pending |
| Sep 08, 2021 | 30 day Public Notice Issued |
| Oct 08, 2021 | Public Notice End Date |
| Oct 14, 2021 | Dock Meeting Scheduled (Admin) |
| Oct 15, 2021 | Stipulation Package from Biologist |
| Oct 15, 2021 | Biologist Report |
| Oct 20, 2021 | Typist for Processing |
| Oct 20, 2021 | Executive Sign Off |
| Oct 20, 2021 | Sent to Photo Copy |
| Oct 20, 2021 | Permit Approved |
| Oct 22, 2021 | Permit Mailed |
| Nov 02, 2021 | Land Evidence Date |
| Dec 03, 2021 | US Army Corps of Engineers Approval Received |