| Action Date | Action Description |
|---|---|
| Sep 02, 2021 | Assent Application Received |
| Sep 08, 2021 | Administrative Review for Completeness |
| Sep 09, 2021 | Bio Team Review for Completeness |
| Sep 09, 2021 | Application Accepted |
| Sep 09, 2021 | Project Manager |
| Sep 24, 2021 | CHA Worksheet received |
| Sep 28, 2021 | Biologist Report |
| Oct 05, 2021 | HPHC Review Pending |
| Oct 05, 2021 | HPHC Historical Preservation No Effect |
| Oct 06, 2021 | Additional Information Received |
| Jan 14, 2022 | Mail Agenda Notice |
| Jan 25, 2022 | Council Approval Granted |
| Jan 25, 2022 | Semi-Monthly Meeting Date Scheduled |
| Feb 10, 2022 | Stipulation Package from Biologist |
| Feb 18, 2022 | Typist for Processing |
| Feb 18, 2022 | Executive Sign Off |
| Feb 18, 2022 | Sent to Photo Copy |
| Feb 18, 2022 | Permit Approved |
| Feb 23, 2022 | Permit Mailed |
| Mar 04, 2022 | Land Evidence Date |
| Mar 10, 2022 | 30 Day Appeal Notification to Owner |
| Mar 10, 2022 | Legal Response/Decision |
| Nov 04, 2024 | Extension of Permit Request |
| Jan 02, 2025 | Enforcement Compliance Inspection Required |
| Jan 06, 2025 | Process Extension |
| Jan 06, 2025 | Extension Approved |
| Jan 06, 2025 | Permit Mailed |