| Action Date | Action Description |
|---|---|
| Legal Response/Decision | |
| US Army Corps of Engineers Approval Required | |
| Sep 27, 2021 | Assent Application Received |
| Sep 30, 2021 | Administrative Review for Completeness |
| Oct 18, 2021 | US Army Corps of Engineers Approval Received |
| Oct 22, 2021 | Application Accepted |
| Oct 22, 2021 | Bio Team Review for Completeness |
| Oct 26, 2021 | Project Manager |
| Oct 26, 2021 | Category A* (Docks) |
| Nov 05, 2021 | HPHC Review Pending |
| Nov 05, 2021 | HPHC Historical Preservation No Effect |
| Nov 22, 2021 | Additional Information Requested from Applicant |
| Dec 16, 2021 | Additional Information Received |
| Dec 21, 2021 | Comments Received |
| Jan 13, 2022 | 30 day Public Notice Issued |
| Feb 11, 2022 | Objections/Comments Received |
| Feb 13, 2022 | Public Notice End Date |
| Feb 16, 2022 | Additional Information Requested from Applicant |
| Apr 04, 2022 | Additional Information Received |
| May 03, 2022 | Plans Received |
| May 10, 2022 | 30 day Public Notice Issued |
| Jun 10, 2022 | Public Notice End Date |
| Jun 16, 2022 | Plans Received |
| Aug 04, 2022 | Ready to Schedule Semi-Monthly Meeting |
| Aug 04, 2022 | Mail Agenda Notice |
| Aug 12, 2022 | Biologist Report |
| Aug 16, 2022 | Continued application |
| Sep 26, 2022 | Mail Agenda Notice |
| Oct 11, 2022 | Council Approval Granted |
| Oct 11, 2022 | Council Approval Granted |
| Oct 11, 2022 | Semi-Monthly Meeting Date Scheduled |
| Oct 17, 2022 | Plans Received |
| Oct 21, 2022 | Stipulation Package from Biologist |
| Jan 19, 2023 | Legal Response/Decision |
| Jan 20, 2023 | 30 Day Appeal Notification to Owner |
| May 01, 2024 | Modification Request |
| May 08, 2024 | Administrative Review for Completeness |
| May 13, 2024 | Application Accepted |
| May 13, 2024 | Project Manager |
| May 14, 2024 | Bio Team Review for Completeness |
| May 28, 2024 | HPHC Historical Preservation No Effect |
| Jun 10, 2024 | Plans Received |
| Jun 11, 2024 | Plans Received |
| Jun 11, 2024 | 30 day Public Notice Issued |
| Jul 11, 2024 | Public Notice End Date |
| Aug 01, 2024 | Mail Agenda Notice |
| Aug 05, 2024 | Entry of Appearance Received |
| Aug 06, 2024 | Biologist Report |
| Aug 27, 2024 | Council Approval Granted |
| Aug 27, 2024 | Semi-Monthly Meeting Date Scheduled |
| Sep 06, 2024 | Stipulation Package from Biologist |
| Oct 11, 2024 | Executive Sign Off |
| Oct 11, 2024 | Sent to Photo Copy |
| Oct 11, 2024 | Modification Approved |
| Oct 11, 2024 | Modification mailed |
| Oct 11, 2024 | Typist for Processing |
| Jan 21, 2025 | Land Evidence Date |