| Action Date | Action Description |
|---|---|
| HPHC Review Pending | |
| Nov 01, 2021 | Assent Application Received |
| Nov 03, 2021 | Administrative Review for Completeness |
| Nov 09, 2021 | Bio Team Review for Completeness |
| Nov 09, 2021 | Application Accepted |
| Nov 09, 2021 | Project Manager |
| Nov 09, 2021 | Category A* (Docks) |
| Nov 17, 2021 | HPHC Review Pending |
| Nov 17, 2021 | HPHC Historical Preservation No Effect |
| Dec 06, 2021 | 30 day Public Notice Issued |
| Jan 06, 2022 | Public Notice End Date |
| May 06, 2022 | Dock Meeting Scheduled (Admin) |
| Jun 08, 2022 | US Army Corps of Engineers Approval Received |
| Sep 14, 2022 | Plans Received |
| Jan 26, 2023 | Typist for Processing |
| Jan 26, 2023 | Executive Sign Off |
| Jan 26, 2023 | Sent to Photo Copy |
| Jan 26, 2023 | Permit Approved |
| Jan 26, 2023 | Engineering Report |
| Jan 27, 2023 | Permit Mailed |
| Feb 08, 2023 | Land Evidence Date |
| Feb 15, 2023 | Commencement of Work Notice received |
| Aug 21, 2023 | Modification Request |
| Aug 21, 2023 | Dock Post-Construction Certification by Engineer received. |
| Aug 25, 2023 | Administrative Review for Completeness |
| Sep 11, 2023 | Bio Team Review for Completeness |
| Sep 11, 2023 | Project Manager |
| Sep 13, 2023 | 30 day Public Notice Issued |
| Oct 13, 2023 | Public Notice End Date |
| Dec 04, 2023 | Plans Received |
| Dec 04, 2023 | Biologist Report |
| Dec 08, 2023 | Modification Approved |
| Dec 13, 2023 | Permit Mailed |
| Apr 05, 2024 | Land Evidence Date |