| Action Date | Action Description |
|---|---|
| Dec 06, 2021 | Assent Application Received |
| Dec 07, 2021 | Administrative Review for Completeness |
| Dec 09, 2021 | Bio Team Review for Completeness |
| Dec 09, 2021 | Application Accepted |
| Dec 09, 2021 | Project Manager |
| Jan 10, 2022 | Correspondence Mailed/Faxed/E-mailed |
| Jan 13, 2022 | HPHC Historical Preservation No Effect |
| Jan 13, 2022 | HPHC Review Pending |
| Apr 27, 2022 | Biologist Report |
| Apr 29, 2022 | Typist for Processing |
| Apr 29, 2022 | Executive Sign Off |
| Apr 29, 2022 | Sent to Photo Copy |
| Apr 29, 2022 | Permit Approved |
| May 02, 2022 | Permit Mailed |
| Aug 15, 2022 | Land Evidence Date |