| Action Date | Action Description |
|---|---|
| Dec 23, 2021 | Maintenance Certification Request |
| Dec 30, 2021 | Administrative Review for Completeness |
| Jan 05, 2022 | Eng Team Review for Completeness |
| Jan 05, 2022 | Application Accepted |
| Jan 27, 2022 | Engineering Report |
| Jan 27, 2022 | Typist for Processing |
| Jan 27, 2022 | Executive Sign Off |
| Jan 27, 2022 | Sent to Photo Copy |
| Jan 27, 2022 | Permit Approved |
| Feb 01, 2022 | Permit Mailed |