| Action Date | Action Description |
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| Jun 03, 2022 | Maintenance Certification Request |
| Jun 08, 2022 | Administrative Review for Completeness |
| Jun 13, 2022 | Eng Team Review for Completeness |
| Jun 13, 2022 | Application Accepted |
| Jun 13, 2022 | Project Manager |
| Jun 21, 2022 | HPHC Review Pending |
| Jun 21, 2022 | HPHC Historical Preservation No Effect |
| Jul 21, 2022 | Typist for Processing |
| Jul 21, 2022 | Engineering Report |
| Jul 21, 2022 | Permit Approved |
| Jul 25, 2022 | Permit Mailed |
| Aug 23, 2022 | Land Evidence Date |
| Dec 13, 2024 | Extension of Permit Request |
| Mar 18, 2025 | Duplicate Original Assent requested/mailed |
| May 27, 2025 | Enforcement Compliance Inspection Required |
| May 28, 2025 | Process Extension |
| May 28, 2025 | Extension Approved |