| Action Date | Action Description |
|---|---|
| Jun 21, 2022 | Maintenance Certification Request |
| Jun 22, 2022 | Administrative Review for Completeness |
| Jun 22, 2022 | Bio Team Review for Completeness |
| Jun 23, 2022 | Application Accepted |
| Jun 23, 2022 | Permit Approved |
| Jun 24, 2022 | Permit Mailed |