| Action Date | Action Description |
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| Aug 25, 2022 | Assent Application Received |
| Sep 02, 2022 | Administrative Review for Completeness |
| Sep 02, 2022 | Bio Team Review for Completeness |
| Sep 02, 2022 | Application Accepted |
| Sep 06, 2022 | Project Manager |
| Sep 06, 2022 | Category A* (Docks) |
| Sep 23, 2022 | HPHC Historical Preservation No Effect |
| Oct 04, 2022 | US Army Corps of Engineers Approval Received |
| Oct 22, 2022 | Public Notice End Date |
| Oct 31, 2022 | Biologist Report |
| Oct 31, 2022 | Mail Agenda Notice |
| Nov 09, 2022 | Council Approval Granted |
| Nov 09, 2022 | Semi-Monthly Meeting Date Scheduled |
| Nov 21, 2022 | Stipulation Package from Biologist |
| Jan 17, 2023 | Legal Response/Decision |
| Jan 17, 2023 | 30 Day Appeal Notification to Owner |
| Feb 09, 2023 | Typist for Processing |
| Feb 09, 2023 | Executive Sign Off |
| Feb 09, 2023 | Sent to Photo Copy |
| Feb 09, 2023 | Permit Approved |
| Feb 13, 2023 | Permit Mailed |
| Feb 21, 2023 | Land Evidence Date |