| Action Date | Action Description |
|---|---|
| Mar 27, 2023 | Freshwater Wetlands Application - New - received |
| Mar 30, 2023 | Administrative Review for Completeness |
| Apr 07, 2023 | Bio Team Review for Completeness |
| Apr 07, 2023 | Deficient Application - Owner Notification Sent |
| Apr 27, 2023 | Deficiency Response Received |
| May 03, 2023 | Bio Team Review for Completeness |
| May 03, 2023 | Eng Team Review for Completeness |
| May 03, 2023 | Application Accepted |
| May 03, 2023 | Project Manager |
| May 30, 2023 | HPHC Historical Preservation No Effect |
| Aug 17, 2023 | Additional Information Received |
| Aug 22, 2023 | Biologist Report |
| Aug 22, 2023 | Engineering Report |
| Aug 24, 2023 | Typist for Processing |
| Aug 24, 2023 | Executive Sign Off |
| Aug 24, 2023 | Sent to Photo Copy |
| Aug 24, 2023 | Permit Approved |
| Aug 28, 2023 | Permit Mailed |
| Oct 18, 2024 | Land Evidence Date |