| Action Date | Action Description |
|---|---|
| Land Evidence Date | |
| Apr 07, 2023 | Assent Application Received |
| Apr 13, 2023 | Administrative Review for Completeness |
| Apr 21, 2023 | Eng Team Review for Completeness |
| Apr 21, 2023 | Bio Team Review for Completeness |
| Apr 21, 2023 | Project Manager |
| Apr 21, 2023 | Application Accepted |
| Apr 21, 2023 | Project Manager |
| May 10, 2023 | Engineering Report |
| May 18, 2023 | Typist for Processing |
| May 18, 2023 | Executive Sign Off |
| May 18, 2023 | Sent to Photo Copy |
| May 18, 2023 | Permit Approved |
| May 18, 2023 | Permit Mailed |
| May 26, 2023 | HPHC Historical Preservation No Effect |