| Action Date | Action Description |
|---|---|
| Apr 19, 2023 | Assent Application Received |
| Apr 19, 2023 | CHA Worksheet received |
| Apr 24, 2023 | Administrative Review for Completeness |
| Apr 25, 2023 | Plans Received |
| May 04, 2023 | US Army Corps of Engineers Approval Received |
| May 08, 2023 | Application Accepted |
| May 08, 2023 | Project Manager |
| May 08, 2023 | Eng Team Review for Completeness |
| May 08, 2023 | Bio Team Review for Completeness |
| May 19, 2023 | HPHC Historical Preservation No Effect |
| Jun 19, 2023 | 30 day Public Notice Issued |
| Jul 19, 2023 | Public Notice End Date |
| Sep 06, 2023 | Additional Information Requested from Applicant |
| Sep 13, 2023 | Additional Information Received |
| Oct 02, 2023 | Additional Information Requested from Applicant |
| Oct 02, 2023 | Public Hearing Notices Mailed |
| Oct 02, 2023 | Category B assigned |
| Oct 04, 2023 | Correspondence Received |
| Oct 11, 2023 | Phone Call |
| Oct 11, 2023 | Correspondence Mailed/Faxed/E-mailed |
| Oct 13, 2023 | Biologist Report |
| Oct 13, 2023 | Engineering Report |
| Oct 17, 2023 | Note to File |
| Oct 17, 2023 | Correspondence Mailed/Faxed/E-mailed |
| Oct 17, 2023 | Correspondence Received |
| Oct 18, 2023 | Correspondence Received |
| Oct 24, 2023 | Comments Received |
| Oct 24, 2023 | Semi-Monthly Meeting Held |
| Oct 24, 2023 | Continued Application by the Council |
| Oct 25, 2023 | Comments Received |
| Oct 26, 2023 | Comments Received |
| Oct 26, 2023 | Correspondence Received |
| Oct 27, 2023 | Correspondence Received |
| Oct 30, 2023 | Comments Received |
| Nov 01, 2023 | Objections/Comments Received |
| Nov 03, 2023 | Comments Received |
| Nov 07, 2023 | Correspondence Received |
| Nov 14, 2023 | Correspondence Received |
| Nov 17, 2023 | Correspondence Received |
| Nov 22, 2023 | Comments Received |
| Nov 24, 2023 | Comments Received |
| Nov 29, 2023 | Correspondence Received |
| Nov 29, 2023 | Meeting Held |
| Dec 04, 2023 | Correspondence Received |
| Feb 05, 2024 | Correspondence Received |
| Feb 07, 2024 | Additional Information Received |
| Feb 21, 2024 | Phone Call |
| Feb 21, 2024 | Additional Information Requested from Applicant |
| Feb 23, 2024 | 30 day Public Notice Issued |
| Mar 04, 2024 | Correspondence Received |
| Mar 05, 2024 | Correspondence Received |
| Mar 12, 2024 | Correspondence Received |
| Mar 13, 2024 | Correspondence Received |
| Mar 15, 2024 | Comments Received |
| Mar 25, 2024 | Objections/Comments Received |
| Mar 25, 2024 | Objections/Comments Received |
| Mar 25, 2024 | Public Notice End Date |
| Apr 09, 2024 | Mail Agenda Notice |
| Apr 09, 2024 | Ready to Schedule Semi-Monthly Meeting |
| Apr 16, 2024 | Meeting Held |
| Apr 18, 2024 | Plans Received |
| Apr 19, 2024 | Letter of Support for Project |
| Apr 24, 2024 | Continued application |
| Apr 30, 2024 | Comments Received |
| May 06, 2024 | Additional Information Received |
| May 14, 2024 | Semi-Monthly Meeting Postponed |
| May 17, 2024 | Additional Information Received |
| May 28, 2024 | Council Approval Granted |
| May 28, 2024 | Semi-Monthly Meeting Date Scheduled |
| Jun 26, 2024 | Stipulation Package from Biologist |
| Jun 28, 2024 | Stipulation Package by Engineer |
| Jul 01, 2024 | Legal Response/Decision |
| Jul 01, 2024 | Typist for Processing |
| Jul 01, 2024 | Permit Approved |
| Jul 03, 2024 | Permit Mailed |
| Jul 11, 2024 | Commencement of Work Notice received |
| Jul 11, 2024 | Correspondence Received |
| Oct 02, 2024 | Land Evidence Date |