| Action Date | Action Description |
|---|---|
| Jun 20, 2023 | Freshwater Wetlands Application - New - received |
| Jun 22, 2023 | Administrative Review for Completeness |
| Jul 12, 2023 | Bio Team Review for Completeness |
| Jul 12, 2023 | Application Accepted |
| Jul 12, 2023 | Project Manager |
| Aug 08, 2023 | HPHC Historical Preservation Comments/Concerns |
| Sep 07, 2023 | HPHC Historical Preservation No Effect |
| Oct 04, 2023 | Biologist Report |
| Oct 05, 2023 | Typist for Processing |
| Oct 05, 2023 | Executive Sign Off |
| Oct 05, 2023 | Sent to Photo Copy |
| Oct 05, 2023 | Permit Approved |
| Oct 06, 2023 | Permit Mailed |