| Action Date | Action Description |
|---|---|
| Jun 27, 2023 | Assent Application Received |
| Jun 30, 2023 | Administrative Review for Completeness |
| Jul 05, 2023 | Bio Team Review for Completeness |
| Jul 05, 2023 | Application Accepted |
| Jul 05, 2023 | Project Manager |
| Aug 17, 2023 | HPHC Historical Preservation No Effect |
| Sep 08, 2023 | Additional Information Received |
| Nov 20, 2023 | Additional Information Received |
| Nov 29, 2023 | Plans Received |
| Dec 01, 2023 | Biologist Report |
| Dec 04, 2023 | Typist for Processing |
| Dec 04, 2023 | Executive Sign Off |
| Dec 04, 2023 | Sent to Photo Copy |
| Dec 04, 2023 | Permit Approved |
| Dec 06, 2023 | Permit Mailed |
| Dec 28, 2023 | Land Evidence Date |