| Action Date | Action Description |
|---|---|
| Jul 21, 2023 | Assent Application Received |
| Jul 27, 2023 | Administrative Review for Completeness |
| Jul 28, 2023 | Bio Team Review for Completeness |
| Jul 28, 2023 | Application Accepted |
| Jul 28, 2023 | Project Manager |
| Aug 04, 2023 | HPHC Historical Preservation No Effect |
| Aug 31, 2023 | Additional Information Requested from Applicant |
| Sep 22, 2023 | Correspondence Received |
| Sep 22, 2023 | Correspondence Mailed/Faxed/E-mailed |
| Nov 14, 2023 | Correspondence Received |
| Nov 30, 2023 | Additional Information Received |
| Dec 05, 2023 | Additional Information Received |
| Jan 30, 2024 | Additional Information Requested from Applicant |
| Feb 21, 2024 | Plans Received |
| Mar 07, 2024 | Biologist Report |
| Mar 08, 2024 | Typist for Processing |
| Mar 08, 2024 | Executive Sign Off |
| Mar 08, 2024 | Sent to Photo Copy |
| Mar 08, 2024 | Permit Approved |
| Mar 12, 2024 | Permit Mailed |
| Sep 30, 2024 | Land Evidence Date |