| Action Date | Action Description |
|---|---|
| Land Evidence Date | |
| Oct 19, 2023 | Assent Application Received |
| Oct 19, 2023 | CHA Worksheet received |
| Oct 24, 2023 | Administrative Review for Completeness |
| Oct 30, 2023 | Bio Team Review for Completeness |
| Oct 30, 2023 | Application Accepted |
| Oct 30, 2023 | Project Manager |
| Nov 24, 2023 | HPHC Historical Preservation No Effect |
| Dec 19, 2023 | 30 day Public Notice Issued |
| Jan 19, 2024 | Public Notice End Date |
| Feb 14, 2024 | Comments Received |
| Feb 28, 2024 | Mail Agenda Notice |
| Mar 12, 2024 | Semi-Monthly Meeting Date Scheduled |
| Jun 18, 2024 | Additional Information Received |
| Aug 01, 2024 | Biologist Report |
| Aug 01, 2024 | Engineering Report |
| Aug 05, 2024 | Typist for Processing |
| Aug 05, 2024 | Executive Sign Off |
| Aug 05, 2024 | Sent to Photo Copy |
| Aug 05, 2024 | Permit Approved |
| Aug 07, 2024 | Permit Mailed |