| Action Date | Action Description |
|---|---|
| Nov 30, 2023 | Assent Application Received |
| Dec 01, 2023 | Administrative Review for Completeness |
| Dec 11, 2023 | Bio Team Review for Completeness |
| Dec 11, 2023 | Application Accepted |
| Dec 11, 2023 | Project Manager |
| Dec 12, 2023 | Plans Received |
| Jan 26, 2024 | Plans Received |
| Feb 16, 2024 | Plans Received |
| Feb 20, 2024 | HPHC Historical Preservation No Effect |
| Feb 20, 2024 | Typist for Processing |
| Feb 20, 2024 | Executive Sign Off |
| Feb 20, 2024 | Sent to Photo Copy |
| Feb 20, 2024 | Permit Approved |
| Feb 20, 2024 | Biologist Report |
| Feb 22, 2024 | Permit Mailed |
| Mar 01, 2024 | Land Evidence Date |
| Mar 18, 2024 | Commencement of Work Notice received |
| Apr 07, 2025 | Modification Request |
| Apr 10, 2025 | Administrative Review for Completeness |
| Apr 25, 2025 | Bio Team Review for Completeness |
| Apr 25, 2025 | Project Manager |
| Apr 29, 2025 | Biologist Report |
| Jun 13, 2025 | HPHC Historical Preservation No Effect |
| Jun 16, 2025 | Plans Received |
| Jun 17, 2025 | Executive Sign Off |
| Jun 17, 2025 | Modification Approved |
| Jun 17, 2025 | Typist for Processing |
| Jun 18, 2025 | Modification mailed |