| Action Date | Action Description |
|---|---|
| Aug 07, 2024 | Assent Application Received |
| Aug 13, 2024 | Administrative Review for Completeness |
| Aug 15, 2024 | Bio Team Review for Completeness |
| Aug 15, 2024 | Application Accepted |
| Aug 15, 2024 | Project Manager |
| Aug 30, 2024 | HPHC Historical Preservation No Effect |
| Sep 18, 2024 | 30 day Public Notice Issued |
| Oct 18, 2024 | Public Notice End Date |
| Dec 20, 2024 | Dock Meeting -- Approval |
| Dec 31, 2024 | Biologist Report |
| Jan 03, 2025 | Permit Mailed |
| Jan 03, 2025 | Typist for Processing |
| Jan 03, 2025 | Executive Sign Off |
| Jan 03, 2025 | Sent to Photo Copy |
| Jan 03, 2025 | Permit Approved |
| Jan 16, 2025 | Land Evidence Date |
| Jul 18, 2025 | Commencement of Work Notice received |
| Oct 08, 2025 | Additional Information Received |
| Oct 14, 2025 | Dock Post-Construction Certification by Engineer received. |