| Action Date | Action Description |
|---|---|
| Dec 13, 2024 | Assent Application Received |
| Dec 17, 2024 | Administrative Review for Completeness |
| Dec 17, 2024 | Bio Team Review for Completeness |
| Dec 17, 2024 | Application Accepted |
| Dec 26, 2024 | Finding Of No Significant Impact (FONSI) |
| Dec 27, 2024 | Permit Mailed |