| Action Date | Action Description |
|---|---|
| Land Evidence Date | |
| Feb 26, 2025 | Assent Application Received |
| Mar 03, 2025 | Administrative Review for Completeness |
| Mar 04, 2025 | Bio Team Review for Completeness |
| Mar 04, 2025 | Project Manager |
| Mar 04, 2025 | Application Accepted |
| Apr 10, 2025 | HPHC Historical Preservation No Effect |
| Jun 20, 2025 | CHA Worksheet received |
| Jun 20, 2025 | Additional Information Received |
| Jul 18, 2025 | Biologist Report |
| Jul 30, 2025 | Typist for Processing |
| Jul 30, 2025 | Executive Sign Off |
| Jul 30, 2025 | Sent to Photo Copy |
| Jul 30, 2025 | Permit Approved |
| Aug 05, 2025 | Permit Mailed |
| Aug 15, 2025 | Note to File |
| Aug 18, 2025 | Land Evidence Date |
| Sep 17, 2025 | Modification Request |
| Sep 24, 2025 | Administrative Review for Completeness |
| Sep 26, 2025 | Bio Team Review for Completeness |
| Sep 26, 2025 | Project Manager |
| Sep 26, 2025 | Application Accepted |
| Oct 07, 2025 | Biologist Report |
| Oct 08, 2025 | Typist for Processing |
| Oct 08, 2025 | Executive Sign Off |
| Oct 08, 2025 | Sent to Photo Copy |
| Oct 08, 2025 | Modification Approved |
| Oct 08, 2025 | Modification mailed |
| Oct 14, 2025 | HPHC Historical Preservation No Effect |
| Oct 15, 2025 | Permit Mailed |