| Action Date | Action Description |
|---|---|
| Mar 03, 2025 | Assent Application Received |
| Mar 06, 2025 | Administrative Review for Completeness |
| Mar 11, 2025 | Eng Team Review for Completeness |
| Mar 11, 2025 | Bio Team Review for Completeness |
| Mar 11, 2025 | Application Accepted |
| Mar 11, 2025 | Project Manager |
| Mar 18, 2025 | Engineering Report |
| Mar 26, 2025 | Typist for Processing |
| Mar 27, 2025 | Executive Sign Off |
| Mar 27, 2025 | Permit Approved |
| Mar 27, 2025 | Permit Mailed |
| Mar 31, 2025 | HPHC Historical Preservation No Effect |
| Sep 05, 2025 | Additional Information Received |