| Action Date | Action Description |
|---|---|
| Mar 06, 2025 | Assent Application Received |
| Mar 12, 2025 | Administrative Review for Completeness |
| Mar 26, 2025 | Bio Team Review for Completeness |
| Mar 26, 2025 | Project Manager |
| Mar 26, 2025 | Application Accepted |
| Apr 10, 2025 | HPHC Historical Preservation No Effect |
| Jun 24, 2025 | Additional Information Requested from Applicant |
| Jul 07, 2025 | Additional Information Received |
| Jul 10, 2025 | Biologist Report |
| Jul 15, 2025 | Typist for Processing |
| Jul 15, 2025 | Executive Sign Off |
| Jul 15, 2025 | Sent to Photo Copy |
| Jul 15, 2025 | Permit Approved |
| Jul 18, 2025 | Permit Mailed |
| Aug 07, 2025 | US Army Corps of Engineers Approval Received |
| Aug 28, 2025 | Additional Information Received |
| Sep 17, 2025 | Commencement of Work Notice received |