| Action Date | Action Description |
|---|---|
| Land Evidence Date | |
| Jul 25, 2025 | Assent Application Received |
| Jul 28, 2025 | Administrative Review for Completeness |
| Jul 30, 2025 | Bio Team Review for Completeness |
| Jul 30, 2025 | Project Manager |
| Jul 30, 2025 | Application Accepted |
| Aug 20, 2025 | HPHC Historical Preservation No Effect |
| Sep 25, 2025 | Typist for Processing |
| Sep 25, 2025 | Executive Sign Off |
| Sep 25, 2025 | Sent to Photo Copy |
| Sep 25, 2025 | Permit Approved |
| Sep 25, 2025 | Biologist Report |
| Sep 25, 2025 | Dock Post-Construction Certification by Engineer Required. |
| Sep 29, 2025 | Permit Mailed |