| Action Date | Action Description |
|---|---|
| Jun 19, 1995 | Application Accepted |
| Jul 20, 1995 | Biologist Report |
| Aug 01, 1995 | Permit Approved |
| Aug 01, 1995 | Land Evidence Date |
| Jan 13, 2010 | Correspondence Received |
| Sep 13, 2010 | Modification Request |
| Sep 13, 2010 | Administrative Review for Completeness |
| Sep 17, 2010 | Team Review for Completeness |
| Sep 17, 2010 | Team Review for Completeness |
| Oct 07, 2010 | HPHC Historical Preservation No Effect |
| Feb 01, 2011 | Additional Information Requested from Applicant |
| Apr 06, 2011 | 30-Day Notification of Cancellation letter |
| Apr 08, 2011 | Certified Receipt Received |
| Apr 28, 2011 | Correspondence Received |
| May 04, 2011 | Additional Information Requested from Applicant |
| Jul 29, 2011 | Additional Information Received |
| Sep 01, 2011 | Additional Information Received |
| Sep 09, 2011 | 30 day Public Notice Issued |
| Oct 09, 2011 | Public Notice End Date |
| Dec 07, 2011 | Biologist Report |
| Dec 07, 2011 | Engineering Report |
| Dec 13, 2011 | Land Evidence Date |
| Dec 28, 2011 | Modification Approved |
| Dec 28, 2011 | Typist for Processing |
| Dec 30, 2011 | Executive Sign Off |
| Dec 30, 2011 | Sent to Photo Copy |
| Jan 23, 2012 | Land Evidence Date |
| Mar 19, 2012 | US Army Corps of Engineers Approval Received |