| Action Date | Action Description |
|---|---|
| May 03, 2001 | ISDS Approved |
| Mar 11, 2002 | Application Accepted |
| Apr 03, 2002 | 30 day Public Notice Issued |
| Oct 06, 2004 | Additional Information Requested from Applicant |
| Oct 06, 2004 | 30-Day Notification of Cancellation letter |
| Jan 19, 2005 | Biologist Report |
| Jan 19, 2005 | Engineering Report |
| Jan 19, 2005 | Stipulation Package by Engineer |
| Jan 19, 2005 | Stipulation Package from Biologist |
| Jan 20, 2005 | Typist for Processing |
| Jan 20, 2005 | Executive Sign Off |
| Jan 20, 2005 | Permit Approved |
| Jan 22, 2005 | Sent to Photo Copy |
| Feb 07, 2005 | Land Evidence Date |
| Apr 07, 2005 | Correspondence Mailed/Faxed/E-mailed |
| Jun 21, 2005 | Correspondence Mailed/Faxed/E-mailed |
| Nov 04, 2005 | Modification Request |
| Nov 10, 2005 | Administrative Review for Completeness |
| Nov 15, 2005 | Team Review for Completeness |
| Dec 01, 2005 | HPHC Historical Preservation No Effect |
| Dec 06, 2005 | Biologist Report |
| Dec 06, 2005 | Engineering Report |
| Dec 12, 2005 | Typist for Processing |
| Dec 12, 2005 | Executive Sign Off |
| Dec 12, 2005 | Sent to Photo Copy |
| Dec 12, 2005 | Modification Approved |
| Dec 21, 2005 | Land Evidence Date |
| Apr 26, 2006 | Modification Request |
| May 01, 2006 | Administrative Review for Completeness |
| May 01, 2006 | Team Review for Completeness |
| May 12, 2006 | HPHC Historical Preservation No Effect |
| Jul 31, 2006 | Plans Received |
| Aug 08, 2006 | Engineering Report |
| Aug 08, 2006 | Biologist Report |
| Aug 10, 2006 | Typist for Processing |
| Aug 10, 2006 | Executive Sign Off |
| Aug 10, 2006 | Sent to Photo Copy |
| Aug 10, 2006 | Modification Approved |
| Aug 15, 2006 | Land Evidence Date |