| Action Date | Action Description |
|---|---|
| Violation Exists on this Site (C&D Order) | |
| Violation Exists on this Site (NOV) | |
| Monitoring Report | |
| Dec 03, 2003 | Application Accepted |
| Dec 31, 2003 | Historical Preservation Approval Granted |
| Apr 07, 2004 | Correspondence Received |
| Jul 22, 2004 | Correspondence Received |
| Aug 12, 2004 | Correspondence Received |
| Aug 23, 2004 | Correspondence Received |
| Sep 16, 2004 | 30 day Public Notice Issued |
| Nov 05, 2004 | Dredge Report |
| Nov 05, 2004 | Biologist Report |
| Nov 05, 2004 | Engineering Report |
| Dec 17, 2004 | Correspondence Received |
| Dec 17, 2004 | Correspondence Received |
| Feb 11, 2005 | Ready to Schedule Semi-Monthly Meeting |
| Feb 11, 2005 | Semi-Monthly Meeting Date Scheduled |
| Feb 15, 2005 | Mail Agenda Notice |
| Feb 17, 2005 | Correspondence Received |
| Feb 22, 2005 | Semi-Monthly Meeting Held |
| Mar 18, 2005 | Additional Information Received |
| Mar 18, 2005 | Plans Received |
| Apr 28, 2005 | Additional Information Received |
| Jul 05, 2005 | Joint Public Notice |
| Aug 05, 2005 | Public Notice End Date |
| Aug 05, 2005 | Objections/Comments Received |
| Aug 09, 2005 | Correspondence Received |
| Sep 09, 2005 | Engineering Report |
| Sep 12, 2005 | Biologist Report |
| Sep 14, 2005 | Correspondence Received |
| Sep 15, 2005 | Mail Agenda Notice |
| Sep 22, 2005 | Continuance Requested by Applicant |
| Sep 23, 2005 | Continuance request by applicant granted by Director |
| Sep 27, 2005 | Semi-Monthly Meeting Date Scheduled |
| Oct 07, 2005 | Correspondence Received |
| Oct 25, 2005 | Semi-Monthly Meeting Date Scheduled |
| Nov 01, 2005 | Correspondence Received |
| Nov 04, 2005 | Mail Agenda Notice |
| Nov 08, 2005 | Continued Application by the Council |
| Nov 08, 2005 | Correspondence Mailed/Faxed/E-mailed |
| Nov 18, 2005 | Plans Received |
| Nov 30, 2005 | Additional Information Received |
| Dec 07, 2005 | Mail Agenda Notice |
| Dec 13, 2005 | Semi-Monthly Meeting Date Scheduled |
| Jan 03, 2006 | Mail Agenda Notice |
| Jan 10, 2006 | Correspondence Received |
| Jan 10, 2006 | Semi-Monthly Meeting Held |
| Jan 10, 2006 | Council Approval Granted |
| Jan 10, 2006 | Semi-Monthly Meeting Date Scheduled |
| Jan 13, 2006 | Legal Response/Decision |
| Jan 13, 2006 | Typist for Processing |
| Jan 13, 2006 | Executive Sign Off |
| Jan 13, 2006 | Sent to Photo Copy |
| Jan 13, 2006 | Permit Approved |
| Jan 18, 2006 | Stipulation Package from Biologist |
| Jan 18, 2006 | Stipulation Package by Engineer |
| Jan 19, 2006 | Commencement of Work Notice received |
| Jan 19, 2006 | Correspondence Received |
| Jan 19, 2006 | Correspondence Received |
| Jan 20, 2006 | Land Evidence Date |
| Jan 20, 2006 | Correspondence Mailed/Faxed/E-mailed |
| Jan 30, 2006 | Modification Request |
| Jan 30, 2006 | Administrative Review for Completeness |
| Jan 30, 2006 | Team Review for Completeness |
| Mar 30, 2006 | Correspondence Received |
| Mar 30, 2006 | Monitoring Report |
| Apr 12, 2006 | Commencement of Work Notice received |
| May 11, 2006 | Monitoring Report |
| Jun 27, 2006 | Monitoring Report |
| Jul 14, 2006 | Correspondence Mailed/Faxed/E-mailed |
| Jul 20, 2006 | Monitoring Report |
| Aug 24, 2006 | Engineering Report |
| Aug 24, 2006 | Biologist Report |
| Aug 24, 2006 | Modification Approved |
| Sep 12, 2006 | Land Evidence Date |
| Nov 21, 2006 | Monitoring Report |
| Jan 09, 2007 | Monitoring Report |
| Jan 18, 2007 | Monitoring Report |
| Feb 13, 2007 | Correspondence Received |
| Apr 10, 2007 | Modification Request |
| Apr 11, 2007 | Administrative Review for Completeness |
| Apr 30, 2007 | Correspondence Received |
| Apr 30, 2007 | Monitoring Report |
| Oct 25, 2007 | Modification Request |
| Oct 26, 2007 | Administrative Review for Completeness |
| Oct 26, 2007 | Team Review for Completeness |
| Nov 01, 2007 | HPHC Historical Preservation No Effect |
| Dec 06, 2007 | Additional Information Received |
| Jul 13, 2009 | Correspondence Mailed/Faxed/E-mailed |
| Mar 01, 2010 | Modification Canceled |
| Jun 11, 2012 | Correspondence Received |
| Nov 05, 2013 | Correspondence Received |
| Feb 26, 2014 | Modification Request |
| Feb 26, 2014 | Modification Approved |
| Feb 26, 2014 | Biologist Report |
| Feb 26, 2014 | Letter of Authorization |
| Feb 27, 2014 | Land Evidence Date |
| Oct 10, 2014 | Monitoring Report |