| Action Date | Action Description |
|---|---|
| Apr 25, 2005 | Assent Application Received |
| Apr 25, 2005 | Administrative Review for Completeness |
| Apr 29, 2005 | Deficient Application - Owner Notification Sent |
| May 05, 2005 | Deficiency Response Received |
| May 06, 2005 | Team Review for Completeness |
| May 06, 2005 | Application Accepted |
| May 06, 2005 | Category A* (Docks) |
| May 17, 2005 | 30 day Public Notice Issued |
| May 20, 2005 | Historical Preservation Approval Granted |
| May 20, 2005 | HPHC Review Pending |
| Jun 17, 2005 | Public Notice End Date |
| Jun 17, 2005 | Objections/Comments Received |
| Jun 20, 2005 | Correspondence Received |
| Jul 28, 2005 | US Army Corp of Engineers Permit Date |
| Jul 29, 2005 | US Army Corps of Engineers Approval Received |
| Dec 02, 2005 | Engineering Report |
| Dec 02, 2005 | Biologist Report |
| Dec 08, 2005 | Executive Sign Off |
| Jan 18, 2006 | Plans Received |
| Feb 23, 2006 | Mail Agenda Notice |
| Feb 23, 2006 | Ready to Schedule Semi-Monthly Meeting |
| Mar 09, 2006 | Correspondence Received |
| Mar 14, 2006 | Semi-Monthly Meeting Date Scheduled |
| Mar 21, 2006 | Mail Agenda Notice |
| Mar 24, 2006 | Correspondence Received |
| Mar 28, 2006 | Semi-Monthly Meeting Held |
| Mar 28, 2006 | Council Approval Granted |
| Mar 28, 2006 | Semi-Monthly Meeting Date Scheduled |
| Apr 05, 2006 | Stipulation Package from Biologist |
| Apr 05, 2006 | Stipulation Package by Engineer |
| Apr 05, 2006 | Typist for Processing |
| Apr 05, 2006 | Executive Sign Off |
| Apr 05, 2006 | Sent to Photo Copy |
| Apr 05, 2006 | Permit Approved |
| Apr 11, 2006 | Legal Response/Decision |
| May 18, 2006 | Land Evidence Date |
| May 30, 2006 | Commencement of Work Notice received |
| Oct 10, 2006 | Correspondence Received |