| Action Date | Action Description |
|---|---|
| May 16, 2005 | Assent Application Received |
| May 16, 2005 | Administrative Review for Completeness |
| May 26, 2005 | Team Review for Completeness |
| May 26, 2005 | Application Accepted |
| Jun 10, 2005 | HPHC Review Pending |
| Oct 02, 2007 | Engineering Report |
| Oct 02, 2007 | Typist for Processing |
| Oct 02, 2007 | Executive Sign Off |
| Oct 02, 2007 | Sent to Photo Copy |
| Oct 02, 2007 | Permit Approved |
| Oct 12, 2007 | Land Evidence Date |
| Jul 10, 2008 | Correspondence Received |
| Nov 10, 2008 | Correspondence Received |
| Oct 21, 2009 | Commencement of Work Notice received |