| Action Date | Action Description |
|---|---|
| Feb 11, 2010 | Assent Application Received |
| Feb 11, 2010 | Administrative Review for Completeness |
| Feb 16, 2010 | Team Review for Completeness |
| Feb 16, 2010 | Team Review for Completeness |
| Feb 16, 2010 | Deficient Application - Owner Notification Sent |
| Mar 17, 2010 | Deficiency Response Received |
| Mar 25, 2010 | Team Review for Completeness |
| Mar 25, 2010 | Team Review for Completeness |
| Mar 25, 2010 | Application Accepted |
| Apr 16, 2010 | HPHC Historical Preservation No Effect |
| May 25, 2010 | Additional Information Received |
| Jul 15, 2010 | Biologist Report |
| Jul 15, 2010 | Engineering Report |
| Jul 16, 2010 | Typist for Processing |
| Jul 16, 2010 | Permit Approved |
| Jul 19, 2010 | Executive Sign Off |
| Jul 20, 2010 | Sent to Photo Copy |
| Aug 23, 2010 | Land Evidence Date |