| Action Date | Action Description |
|---|---|
| Jul 01, 2010 | Administrative Review for Completeness |
| Jul 13, 2010 | Team Review for Completeness |
| Jul 13, 2010 | Team Review for Completeness |
| Jul 13, 2010 | Deficient Application - Owner Notification Sent |
| Nov 09, 2010 | Deficiency Response Received |
| Nov 15, 2010 | Team Review for Completeness |
| Nov 15, 2010 | Team Review for Completeness |
| Nov 15, 2010 | Application Accepted |
| Nov 22, 2010 | Biologist Report |
| Nov 22, 2010 | Engineering Report |
| Nov 22, 2010 | Assent Application Received |
| Nov 29, 2010 | Permit Approved |
| Nov 29, 2010 | Typist for Processing |
| Dec 01, 2010 | Executive Sign Off |
| Dec 01, 2010 | Sent to Photo Copy |
| Dec 02, 2010 | HPHC Historical Preservation No Effect |
| Dec 03, 2010 | Land Evidence Date |
| Mar 22, 2011 | Commencement of Work Notice received |