| Action Date | Action Description |
|---|---|
| Sep 15, 2010 | Assent Application Received |
| Sep 17, 2010 | Administrative Review for Completeness |
| Sep 27, 2010 | Team Review for Completeness |
| Sep 27, 2010 | Team Review for Completeness |
| Sep 27, 2010 | Application Accepted |
| Nov 15, 2010 | 30 day Public Notice Issued |
| Nov 16, 2010 | HPHC Historical Preservation No Effect |
| Dec 15, 2010 | Objections/Comments Received |
| Dec 15, 2010 | Public Notice End Date |
| Jan 18, 2011 | Objections/Comments Received |
| Mar 17, 2011 | Additional Information Received |
| Mar 30, 2011 | Withdrawal Request Received |
| Mar 30, 2011 | US Army Corps of Engineers Approval Received |
| Apr 06, 2011 | Dock Meeting -- Approval |
| Apr 07, 2011 | Biologist Report |
| Apr 07, 2011 | Engineering Report |
| Apr 11, 2011 | Executive Sign Off |
| Apr 11, 2011 | Sent to Photo Copy |
| Apr 12, 2011 | Permit Approved |
| Apr 12, 2011 | Typist for Processing |
| May 06, 2011 | Land Evidence Date |
| Sep 19, 2011 | Commencement of Work Notice received |