| Action Date | Action Description |
|---|---|
| Jul 31, 2012 | Assent Application Received |
| Jul 31, 2012 | Administrative Review for Completeness |
| Aug 17, 2012 | Team Review for Completeness |
| Aug 17, 2012 | Team Review for Completeness |
| Aug 17, 2012 | Deficient Application - Owner Notification Sent |
| Aug 23, 2012 | Deficient Application Picked Up |
| Oct 09, 2012 | Deficiency Response Received |
| Oct 15, 2012 | Team Review for Completeness |
| Oct 15, 2012 | Team Review for Completeness |
| Oct 15, 2012 | Deficient Application - Owner Notification Sent |
| Oct 19, 2012 | Deficiency Response Received |
| Oct 23, 2012 | Team Review for Completeness |
| Oct 23, 2012 | Team Review for Completeness |
| Oct 23, 2012 | Application Accepted |
| Oct 23, 2012 | Category B assigned |
| Nov 01, 2012 | HPHC Historical Preservation No Effect |
| Nov 13, 2012 | Public Notice End Date |
| Dec 13, 2012 | 30 day Public Notice Issued |
| Jan 02, 2013 | Public Notice End Date Extension Granted |
| Jan 10, 2013 | Objections/Comments Received |
| Jan 11, 2013 | Objections/Comments Received |
| Jan 17, 2013 | Correspondence Received |
| Jan 18, 2013 | Correspondence Received |
| Jan 22, 2013 | Objections/Comments Received |
| Jan 22, 2013 | Objections/Comments Received |
| Jan 22, 2013 | Objections/Comments Received |
| Jan 22, 2013 | Objections/Comments Received |
| Jan 22, 2013 | Objections/Comments Received |
| Jan 22, 2013 | Objections/Comments Received |
| Jan 22, 2013 | Objections/Comments Received |
| Mar 07, 2013 | Withdrawal Confirmation Mailed |
| Mar 07, 2013 | Biologist Report |
| Mar 07, 2013 | Engineering Report |
| Mar 22, 2013 | Correspondence Received |
| Mar 26, 2013 | Correspondence Mailed/Faxed/E-mailed |