| Action Date | Action Description |
|---|---|
| Nov 26, 2012 | Buffer Zone Management Application Received |
| Nov 27, 2012 | Administrative Review for Completeness |
| Dec 04, 2012 | Team Review for Completeness |
| Dec 04, 2012 | Team Review for Completeness |
| Dec 04, 2012 | Application Accepted |
| Dec 13, 2012 | HPHC Historical Preservation No Effect |
| Feb 07, 2013 | Typist for Processing |
| Feb 07, 2013 | Biologist Report |
| Feb 07, 2013 | Engineering Report |
| Feb 07, 2013 | Permit Approved |
| Feb 13, 2013 | Executive Sign Off |
| Feb 13, 2013 | Sent to Photo Copy |
| Mar 06, 2013 | Land Evidence Date |
| Apr 26, 2013 | Modification Request |
| Apr 29, 2013 | Administrative Review for Completeness |
| Apr 30, 2013 | Team Review for Completeness |
| Apr 30, 2013 | Team Review for Completeness |
| May 15, 2013 | Biologist Report |
| May 15, 2013 | Engineering Report |
| May 16, 2013 | Typist for Processing |
| May 16, 2013 | HPHC Historical Preservation No Effect |
| May 16, 2013 | Modification Approved |
| May 17, 2013 | Executive Sign Off |
| May 17, 2013 | Sent to Photo Copy |
| May 23, 2013 | Land Evidence Date |
| Nov 06, 2013 | Monitoring Report |
| Oct 15, 2014 | Monitoring Report |
| Nov 27, 2015 | Monitoring Report |
| Nov 09, 2016 | Monitoring Report |