| Action Date | Action Description |
|---|---|
| Nov 30, 2012 | Assent Application Received |
| Dec 03, 2012 | Administrative Review for Completeness |
| Dec 04, 2012 | Team Review for Completeness |
| Dec 04, 2012 | Team Review for Completeness |
| Dec 04, 2012 | Application Accepted |
| Dec 13, 2012 | HPHC Historical Preservation No Effect |
| Feb 05, 2013 | 30 day Public Notice Issued |
| Mar 05, 2013 | Public Notice End Date |
| Mar 18, 2013 | Biologist Report |
| Mar 18, 2013 | Engineering Report |
| Mar 22, 2013 | Category A* (Docks) |
| Mar 22, 2013 | Typist for Processing |
| Mar 22, 2013 | Permit Approved |
| Mar 25, 2013 | Executive Sign Off |
| Mar 25, 2013 | Sent to Photo Copy |
| Apr 26, 2013 | US Army Corps of Engineers Approval Received |