| Action Date | Action Description |
|---|---|
| Jan 09, 2013 | Assent Application Received |
| Jan 09, 2013 | Administrative Review for Completeness |
| Jan 24, 2013 | Team Review for Completeness |
| Jan 24, 2013 | Team Review for Completeness |
| Jan 24, 2013 | Deficient Application - Owner Notification Sent |
| Feb 14, 2013 | Deficient Application Picked Up |
| Apr 23, 2013 | Deficiency Response Received |
| Apr 29, 2013 | Team Review for Completeness |
| Apr 29, 2013 | Team Review for Completeness |
| Apr 29, 2013 | Application Accepted |
| May 06, 2013 | HPHC Historical Preservation No Effect |
| May 17, 2013 | 30 day Public Notice Issued |
| Jun 14, 2013 | Objections/Comments Received |
| Jun 17, 2013 | Objections/Comments Received |
| Jun 17, 2013 | Public Notice End Date |
| Jun 18, 2013 | Objections/Comments Received |
| Jul 01, 2013 | Objections/Comments Received |
| Jul 18, 2013 | Correspondence Received |
| Sep 16, 2013 | Additional Information Received |
| Oct 02, 2013 | Objections/Comments Received |
| Oct 30, 2013 | Biologist Report |
| Oct 30, 2013 | Engineering Report |
| Oct 30, 2013 | Supervisor Engineer SignOff |
| Nov 04, 2013 | Supervisor Biologist SignOff |
| Nov 06, 2013 | Executive Signoff of Staff Reports |
| Dec 16, 2013 | Ready to Schedule Semi-Monthly Meeting |
| Dec 16, 2013 | Mail Agenda Notice |
| Jan 02, 2014 | Additional Information Received |
| Jan 09, 2014 | Correspondence Received |
| Jan 14, 2014 | Council Approval Granted |
| Jan 14, 2014 | Semi-Monthly Meeting Date Scheduled |
| Jan 14, 2014 | Semi-Monthly Meeting Held |
| Jan 28, 2014 | 30 Day Appeal Notification to Owner |
| Jan 28, 2014 | Legal Response/Decision |
| Mar 05, 2014 | Stipulation Package from Biologist |
| Mar 06, 2014 | Stipulation Package by Engineer |
| Mar 10, 2014 | Typist for Processing |
| Mar 10, 2014 | Permit Approved |
| Mar 11, 2014 | Executive Sign Off |
| Mar 11, 2014 | Sent to Photo Copy |
| Mar 24, 2014 | Land Evidence Date |
| May 07, 2014 | US Army Corps of Engineers Approval Received |
| Jun 13, 2014 | Land Evidence Date |
| Aug 28, 2014 | Assent Correction Request Received |
| Aug 29, 2014 | Assent Correction Mailed |
| Sep 10, 2014 | Land Evidence Date |
| Jun 17, 2015 | Note to File |