| Action Date | Action Description |
|---|---|
| Dec 04, 2014 | Assent Application Received |
| Dec 12, 2014 | Team Review for Completeness |
| Dec 12, 2014 | Application Accepted |
| Dec 12, 2014 | HPHC Historical Preservation No Effect |
| Dec 12, 2014 | Category B assigned |
| Jan 12, 2015 | 30 day Public Notice Issued |
| Jan 23, 2015 | Correspondence Received |
| Feb 12, 2015 | Public Notice End Date |
| Feb 27, 2015 | Objections/Comments Received |
| Mar 02, 2015 | Public Notice End Date |
| Mar 24, 2015 | Mail Agenda Notice |
| Mar 24, 2015 | Plans Received |
| Mar 31, 2015 | Biologist Report |
| Apr 01, 2015 | Supervisor Biologist SignOff |
| Apr 02, 2015 | Executive Signoff of Staff Reports |
| Apr 07, 2015 | Objections/Comments Received |
| Apr 14, 2015 | Semi-Monthly Meeting Date Scheduled |
| Apr 14, 2015 | Council Approval Granted |
| Apr 17, 2015 | Stipulation Package from Biologist |
| Apr 21, 2015 | Typist for Processing |
| Apr 21, 2015 | Executive Sign Off |
| Apr 22, 2015 | Permit Approved |
| May 12, 2015 | Legal Response/Decision |
| Feb 01, 2016 | Modification Request |
| Feb 02, 2016 | Administrative Review for Completeness |
| Feb 05, 2016 | Team Review for Completeness |
| Feb 15, 2016 | Biologist Report |
| Feb 15, 2016 | Typist for Processing |
| Feb 18, 2016 | Executive Sign Off |
| Feb 18, 2016 | Sent to Photo Copy |
| Feb 18, 2016 | Modification Approved |
| Mar 11, 2016 | Land Evidence Date |
| Jan 23, 2017 | Modification Request |
| Jan 25, 2017 | Administrative Review for Completeness |
| Jan 26, 2017 | Team Review for Completeness |
| Jan 26, 2017 | Deficient Application - Owner Notification Sent |
| Jan 11, 2019 | Deficient Application Discarded/No deficiency Reponse |
| Feb 23, 2021 | Modification Request |
| Feb 25, 2021 | Administrative Review for Completeness |
| Mar 03, 2021 | Bio Team Review for Completeness |
| Mar 03, 2021 | Deficient Application - Owner Notification Sent |
| Aug 04, 2021 | Deficiency Response Received |
| Aug 10, 2021 | Administrative Review for Completeness |
| Aug 12, 2021 | Bio Team Review for Completeness |
| Aug 12, 2021 | Project Manager |
| Aug 18, 2021 | 30 day Public Notice Issued |
| Aug 20, 2021 | HPHC Historical Preservation No Effect |
| Aug 20, 2021 | HPHC Review Pending |
| Sep 19, 2021 | Public Notice End Date |
| Sep 24, 2021 | Public Notice End Date Extension Granted |
| Sep 24, 2021 | Comments Received |
| Sep 24, 2021 | Biologist Report |
| Dec 14, 2021 | Dock Meeting -- Approval |
| Jan 13, 2022 | Typist for Processing |
| Jan 13, 2022 | Stipulation Package from Biologist |
| Jan 13, 2022 | Modification Approved |
| Jan 18, 2022 | Permit Mailed |
| Feb 10, 2022 | Commencement of Work Notice received |
| Nov 20, 2024 | Extension of Permit Request |
| Jul 17, 2025 | Enforcement Compliance Inspection Required |
| Jul 18, 2025 | Process Extension |
| Jul 18, 2025 | Extension Approved |