| Action Date | Action Description |
|---|---|
| Sep 07, 2018 | Assent Application Received |
| Sep 10, 2018 | Administrative Review for Completeness |
| Sep 14, 2018 | Team Review for Completeness |
| Sep 27, 2018 | Objections/Comments Received |
| Sep 28, 2018 | Application Accepted |
| Sep 28, 2018 | Team Review for Completeness |
| Sep 28, 2018 | Team Review for Completeness |
| Oct 11, 2018 | 30 day Public Notice Issued |
| Oct 16, 2018 | Objections/Comments Received |
| Oct 17, 2018 | Objections/Comments Received |
| Oct 17, 2018 | Comments Received |
| Oct 18, 2018 | Objections/Comments Received |
| Oct 18, 2018 | HPHC Historical Preservation No Effect |
| Oct 19, 2018 | Objections/Comments Received |
| Oct 22, 2018 | Objections/Comments Received |
| Oct 23, 2018 | Objections/Comments Received |
| Oct 25, 2018 | Objections/Comments Received |
| Oct 26, 2018 | Additional Information Received |
| Oct 31, 2018 | Objections/Comments Received |
| Nov 05, 2018 | Objections/Comments Received |
| Nov 06, 2018 | Objections/Comments Received |
| Nov 07, 2018 | Objections/Comments Received |
| Nov 08, 2018 | Objections/Comments Received |
| Nov 08, 2018 | Objections/Comments Received |
| Nov 09, 2018 | Objections/Comments Received |
| Nov 09, 2018 | Objections/Comments Received |
| Nov 10, 2018 | Objections/Comments Received |
| Nov 11, 2018 | Public Notice End Date |
| Nov 14, 2018 | Additional Information Received |
| Dec 07, 2018 | Additional Information Received |
| Jan 08, 2019 | Additional Information Received |
| Apr 22, 2019 | Engineering Report |
| Apr 24, 2019 | Special Exception Public Hearing Notice mailed |
| Apr 30, 2019 | Biologist Report |
| May 06, 2019 | Additional Information Received |
| May 09, 2019 | Executive Signoff of Staff Reports |
| May 14, 2019 | Council Approval Granted |
| May 14, 2019 | Semi-Monthly Meeting Date Scheduled |
| Jul 03, 2019 | Correspondence Received |
| Jul 17, 2019 | Stipulation Package from Biologist |
| Jul 17, 2019 | Stipulation Package by Engineer |
| Jul 18, 2019 | Legal Response/Decision |
| Jul 18, 2019 | Typist for Processing |
| Jul 18, 2019 | Executive Sign Off |
| Jul 18, 2019 | Sent to Photo Copy |
| Jul 18, 2019 | Permit Approved |
| Jul 24, 2019 | Land Evidence Date |
| Dec 11, 2019 | Monitoring Report |
| Dec 12, 2019 | Monitoring Report |
| Dec 16, 2019 | Monitoring Report |
| Dec 16, 2019 | Correspondence Received |
| Dec 19, 2019 | Monitoring Report |
| Dec 20, 2019 | Monitoring Report |
| Dec 24, 2019 | Monitoring Report |
| Dec 30, 2019 | Monitoring Report |
| Jan 07, 2020 | Correspondence Received |
| Jan 10, 2020 | Monitoring Report |
| Jan 27, 2020 | Monitoring Report |
| Jun 22, 2020 | Modification Request |
| Jun 22, 2020 | Administrative Review for Completeness |
| Jun 25, 2020 | Eng Team Review for Completeness |
| Jun 25, 2020 | Project Manager |
| Jul 08, 2020 | HPHC Historical Preservation No Effect |
| Jul 08, 2020 | HPHC Review Pending |
| Jul 16, 2020 | Typist for Processing |
| Jul 16, 2020 | Modification Approved |
| Jul 16, 2020 | Engineering Report |
| Aug 11, 2020 | Land Evidence Date |
| Jul 17, 2022 | Assent Expiration Date |