| Action Date | Action Description |
|---|---|
| Oct 21, 2019 | Assent Application Received |
| Oct 21, 2019 | Administrative Review for Completeness |
| Oct 23, 2019 | Bio Team Review for Completeness |
| Oct 23, 2019 | Application Accepted |
| Nov 07, 2019 | HPHC Review Pending |
| Nov 07, 2019 | HPHC Historical Preservation No Effect |
| Jan 16, 2020 | Biologist Report |
| Jan 21, 2020 | Typist for Processing |
| Jan 21, 2020 | Executive Sign Off |
| Jan 21, 2020 | Sent to Photo Copy |
| Jan 21, 2020 | Permit Approved |
| Feb 04, 2020 | Land Evidence Date |
| Aug 13, 2020 | Modification Request |
| Aug 13, 2020 | Administrative Review for Completeness |
| Aug 17, 2020 | Bio Team Review for Completeness |
| Aug 18, 2020 | Project Manager |
| Aug 31, 2020 | HPHC Review Pending |
| Aug 31, 2020 | HPHC Historical Preservation No Effect |
| Sep 09, 2020 | Modification Approved |
| Sep 09, 2020 | Biologist Report |