| Action Date | Action Description |
|---|---|
| Jun 26, 2020 | Assent Application Received |
| Jun 29, 2020 | Administrative Review for Completeness |
| Jul 10, 2020 | Bio Team Review for Completeness |
| Jul 10, 2020 | Project Manager |
| Jul 10, 2020 | Application Accepted |
| Jul 24, 2020 | HPHC Review Pending |
| Jul 24, 2020 | HPHC Historical Preservation No Effect |
| Aug 20, 2020 | Plans Received |
| Aug 20, 2020 | Additional Information Received |
| Sep 22, 2020 | Biologist Report |
| Sep 23, 2020 | Typist for Processing |
| Sep 23, 2020 | Executive Sign Off |
| Sep 23, 2020 | Sent to Photo Copy |
| Sep 23, 2020 | Permit Approved |
| Oct 14, 2020 | Land Evidence Date |