| Action Date | Action Description |
|---|---|
| Jul 28, 2020 | Assent Application Received |
| Jul 30, 2020 | Administrative Review for Completeness |
| Jul 31, 2020 | Bio Team Review for Completeness |
| Jul 31, 2020 | Application Accepted |
| Aug 03, 2020 | Project Manager |
| Sep 04, 2020 | HPHC Review Pending |
| Sep 04, 2020 | HPHC Historical Preservation No Effect |
| Sep 23, 2020 | Plans Received |
| Feb 05, 2021 | Stipulation Package from Biologist |
| Feb 05, 2021 | Biologist Report |
| Feb 08, 2021 | Typist for Processing |
| Feb 08, 2021 | Executive Sign Off |
| Feb 08, 2021 | Sent to Photo Copy |
| Feb 08, 2021 | Permit Approved |
| Feb 23, 2021 | Land Evidence Date |
| Jul 06, 2021 | Modification Request |
| Jul 08, 2021 | Administrative Review for Completeness |
| Jul 09, 2021 | Bio Team Review for Completeness |
| Jul 12, 2021 | Additional Information Received |
| Jul 21, 2021 | HPHC Historical Preservation No Effect |
| Jul 21, 2021 | HPHC Review Pending |
| Aug 05, 2021 | Biologist Report |
| Aug 05, 2021 | Stipulation Package from Biologist |
| Aug 10, 2021 | Typist for Processing |
| Aug 10, 2021 | Executive Sign Off |
| Aug 10, 2021 | Sent to Photo Copy |
| Aug 10, 2021 | Modification Approved |
| Aug 18, 2021 | Land Evidence Date |