| Action Date | Action Description |
|---|---|
| Dec 02, 2020 | Assent Application Received |
| Dec 02, 2020 | Administrative Review for Completeness |
| Jan 12, 2021 | Bio Team Review for Completeness |
| Jan 12, 2021 | Application Accepted |
| Jan 13, 2021 | Project Manager |
| Feb 05, 2021 | HPHC Historical Preservation No Effect |
| Feb 05, 2021 | HPHC Review Pending |
| Mar 09, 2021 | Stipulation Package from Biologist |
| Mar 09, 2021 | Typist for Processing |
| Mar 09, 2021 | Executive Sign Off |
| Mar 09, 2021 | Sent to Photo Copy |
| Mar 09, 2021 | Permit Approved |
| Mar 09, 2021 | Biologist Report |
| Jul 07, 2021 | Land Evidence Date |