| Action Date | Action Description |
|---|---|
| Jun 25, 2021 | Buffer Zone Management Application Received |
| Jun 30, 2021 | Administrative Review for Completeness |
| Jul 28, 2021 | Bio Team Review for Completeness |
| Jul 28, 2021 | Deficient Application - Owner Notification Sent |
| Aug 16, 2021 | Deficient Application Picked Up |
| Nov 26, 2021 | Deficiency Response Received |
| Dec 03, 2021 | Bio Team Review for Completeness |
| Dec 03, 2021 | Application Accepted |
| Dec 06, 2021 | Project Manager |
| Dec 15, 2021 | HPHC Historical Preservation No Effect |
| Dec 15, 2021 | HPHC Review Pending |
| May 12, 2022 | Additional Information Received |
| May 13, 2022 | Biologist Report |
| May 16, 2022 | Permit Mailed |
| May 16, 2022 | Typist for Processing |
| May 16, 2022 | Permit Approved |
| May 19, 2022 | Land Evidence Date |