| Action Date | Action Description |
|---|---|
| Jul 15, 2021 | Buffer Zone Management Application Received |
| Jul 16, 2021 | Administrative Review for Completeness |
| Jul 23, 2021 | Bio Team Review for Completeness |
| Jul 23, 2021 | Application Accepted |
| Jul 23, 2021 | Project Manager |
| Aug 20, 2021 | HPHC Review Pending |
| Aug 20, 2021 | HPHC Historical Preservation No Effect |
| Sep 10, 2021 | Additional Information Received |
| Oct 25, 2021 | Correspondence Received |
| Oct 28, 2021 | Correspondence Mailed/Faxed/E-mailed |
| Dec 15, 2021 | Note to File |
| Dec 16, 2021 | Correspondence Mailed/Faxed/E-mailed |
| Jan 05, 2022 | Additional Information Received |
| Feb 16, 2022 | Note to File |
| Mar 02, 2022 | Note to File |
| Mar 02, 2022 | Additional Information Requested from Applicant |
| Mar 31, 2022 | Additional Information Received |
| May 19, 2022 | Biologist Report |
| May 24, 2022 | Permit Mailed |
| May 24, 2022 | Typist for Processing |
| May 24, 2022 | Executive Sign Off |
| May 24, 2022 | Sent to Photo Copy |
| May 24, 2022 | Permit Approved |
| May 27, 2022 | Permit Mailed |
| Jun 06, 2022 | Land Evidence Date |