| Action Date | Action Description |
|---|---|
| Aug 27, 2021 | Assent Application Received |
| Sep 02, 2021 | Administrative Review for Completeness |
| Sep 09, 2021 | Note to File |
| Sep 28, 2021 | Additional Information Received |
| Sep 29, 2021 | Additional Information Received |
| Sep 29, 2021 | Application Accepted |
| Sep 29, 2021 | Bio Team Review for Completeness |
| Oct 25, 2021 | Biologist Report |
| Oct 27, 2021 | Typist for Processing |
| Oct 27, 2021 | HPHC Historical Preservation No Effect |
| Oct 27, 2021 | Executive Sign Off |
| Oct 27, 2021 | Permit Approved |
| Oct 28, 2021 | Permit Mailed |