| Action Date | Action Description |
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| Nov 16, 2021 | Assent Application Received |
| Nov 16, 2021 | Administrative Review for Completeness |
| Nov 26, 2021 | Bio Team Review for Completeness |
| Nov 26, 2021 | Application Accepted |
| Nov 29, 2021 | Project Manager |
| Nov 29, 2021 | Category A* (Docks) |
| Dec 09, 2021 | HPHC Historical Preservation No Effect |
| Dec 09, 2021 | HPHC Review Pending |
| Jan 13, 2022 | 30 day Public Notice Issued |
| Jan 24, 2022 | Additional Information Received |
| Feb 11, 2022 | Dock Meeting -- To Council |
| Feb 13, 2022 | Public Notice End Date |
| Jun 10, 2022 | Additional Information Received |
| Jun 28, 2022 | Biologist Report |
| Jul 06, 2022 | Typist for Processing |
| Jul 06, 2022 | Executive Sign Off |
| Jul 06, 2022 | Sent to Photo Copy |
| Jul 06, 2022 | Permit Approved |
| Jul 06, 2022 | Permit Mailed |
| Jul 18, 2022 | Land Evidence Date |
| Aug 07, 2023 | Commencement of Work Notice received |